Station Way path to be widened

29 April 2016

Improvements to widen the existing path underneath the railway bridge at Station Way, Colchester, are due to start on Tuesday 3 May to provide a new wider 3.5 metre shared footway/cycleway.

 

Work will take place under the bridge on the northbound carriageway between the southern and northern entrances to Colchester Station from 3 May to 7 June 2016.

 

These improvements are part of a wider programme of investment in Colchester to improve local roads, cycleways and footways.

 

Work will be done at night between 20:00 to 05:00 Monday - Friday.  One lane northbound will be closed for 24 hours during the period of the work and pedestrians will be diverted via the signal-controlled crossing point at the Essex Hall Roundabout and across the Colchester Station footbridge.